Oracle ASCP can generate planned orders for an entire supply chain within a single multi-organization supply chain plan.
A single plan of the entire supply chain:
Demand quantity = (Forecast + Actual sales orders)
for each of the time buckets in the planning horizon.
The plan output contains planned order quantities, start dates, and completion dates for all of its components and subcomponents.
Forecast :
Forecast represents the forecast Demand
Sales Order
Sales Order Represent the sales Order Demand
Forecast Consumption:
Forecast consumption is a process that replaces Forecast Demand with the salesOrder.
à Safety stock planned demand
à Forecasts Demand Comes from Oracle Demantra
à Sales order demand
Oracle ASCP outputs a time-phased supply plan (planned orders) that can then be released directly to the appropriate execution systems: Oracle Purchasing, Oracle and Process Manufacturing.
Process of MPS and MRP:
Oracle Advanced Supply Chain Planning considers three streams of independent demand:
à Safety stock planned demand
à Forecasts Demand Comes from Oracle Demantra
à Sales order demand
Oracle ASCP outputs a time-phased supply plan (planned orders) that can then be released directly to the appropriate execution systems: Oracle Purchasing, Oracle and Process Manufacturing.
Process of MPS and MRP:
à Forecast is Published by Demantra
à Standard collections are Run
à MPS plan is Launched to See the Forecast, Planned Order, Planned Order Demand,
On Hand and Sales Order of the Make Item (Finished Goods)
On Hand and Sales Order of the Make Item (Finished Goods)
à MRP is Launched to get see the Planned Order, Planned Order Demand,
On Hand, Purchase Order of the Buy Item ( Ingredients)
On Hand, Purchase Order of the Buy Item ( Ingredients)
à MRP create planned orders for the safety stock if it is defined in the Item Attributes
Planned Order Calculation Will also Depend upon the Item Attributes defined
à Order Modifiers
à Safety Stock
à Order Modifiers
à Safety Stock
Order Modifiers :
Order sizing is a set of item attributes that allow you to control the recommended order quantities for planned orders. The planning process creates planned orders using basic lot-for-lot sizing logic.
àFixed or Variable àFixed Order Quantity à Fixed Lot Multiple à Minimum and Maximum Order Quantity à Fixed Days Supply à Rounding Order Quantities
Safety Stock:
Safety stock is normally required by companies to ensure that they have sufficient quantities of material in stock. The safety stock is there to provide coverage for unexpected customer demand, damage in the warehouse or required due to quality issues found in production.
Planning Detail Report:
The Report Contains all the Details like
■ Action Messages Report
■ MRP Bucketed Material Report
■ MRP Material Activity Report
■ MPS Material Activity Report
■ MPS Bucketed Material Report
■ Reorder Point Report
This report presents a view (within individual time increments that you define) of
the effects of pending inventory transactions on stock quantities; in this manner the
report is similar to the MPS version of the Bucketed Material Report. The MRP
version of the report also shows the effects on inventory quantities of the suggested
actions generated during the most recent MRP run.
You can restrict this report to bucketed material activity for items in one or more
planning classes, or to activity in which one or more planner is concerned.
Report Parameters
===============
===============
Organization
Schedule
Planning Class
Buyer/Planner
Item
For Organization
Warehouse
Report Out Put
Sales Orders
The total sales order demand for the item for each time bucket.
Forecast
The total demand from sales forecasts for each time bucket.
Dependent Demand
The total dependent demand for the item from scheduled batches and firm-planned
orders for each time bucket.
Planned Demand
The sum of planned dependent demand from MRP-planned orders for the item
during each time bucket.
Total Demand
The total demand for the item during each time bucket.
PO Receipts
The total of purchase order receipts of the item during each time bucket. PO receipts
include approved purchase order requisitions, open purchase orders, and planned
purchase order scheduled deliveries.
Schedule Production
The total output from the batches during each time bucket.
Planned Transfer
The total of MRP-suggested warehouse transfers of the item for each time bucket.
Planned Production
The total of MRP-planned batches of the item for each time bucket.
Ending Balance
The on hand item quantity, after all demands and receipts have been applied to the
starting on hand quantity, for each time bucket.
Net SS Requirements
The net safety stock requirement for the time bucket.
Thank you ..!
Financial Restoration Through the help of benjamin lee. Email: 247officedept@gmail.com that's his Email and this is his whatsapp number +1-989-394-3740 . I'mLeonardo Hugo a agronist who was able to revive his dying Livestock Feed Manufacturing through the help of a GodSent lender known as Benjamin Briel Lee the Loan Officer. I want you to know that his Service is the right place for you to resolve all your financial problem because am a living testimony and I can't just keep this to myself when others are looking for a way to be financially lifted. I want you all to contact this God sent lender using the details as stated in other to be a partaker of this great opportunity and also they work with good/reputable bank that wire money transfer without delay into my account.
ReplyDeleteInformation shared here is highly appreciated. Your article has inspired many of us to learn this. You have shared your immense knowledge on Oracle ASCP. Recently one of my friend has taken training from MaxMunus & he was highly satisfied with the quality of the training. If you come across anyone willing to take this training, you can ask them to reach them directly.They are reachable at:-
ReplyDeleteOracle ASCP Training
Nice information. Thanks for sharing such an amazing article. For online training and Self Paced courses visit our site click4learning.com/product/oracle-ascp/
ReplyDelete