Resource requirement outside the resource available time (shift) in constrained plans

Resource Requirement Start Date is outside the resource availability (shift times) in an Enforce Demand Capacity Constrained or Enforce Due Date plan with seemingly no resource constraint


1. Go into the responsibility: Process Engineer

2. Navigate to Process Operations > Activity

3. Check the Breakable checkbox against the resource that is seen as causing the problem. 

4. Go into the responsibility: System Administrator

5. Navigate to Profiles > System Profiles

6. Set the profiles as below:

MSO: Schedule across breaks = Yes
MSO: Schedule simultaneous resources across breaks = Yes
MSO: Respect Activity Contiguity Flag for Process Supplies = No

4. Retest the issue by running the ASCP Standard Collection, complete refresh and the ASCP Plan

5. Migrate the solution as appropriate to other environments.