In order for ASCP to generate planned orders in a fixed quantity dependent on the recipe that is being used for the planned order then the Oracle Inventory Organization Item 'Order Modifiers' of Fix Lot Multiple, Fixed Order Quantity and Order Quantity Minimum and Maximum should be NULL for the product.
The Recipe Validity Rule
Process Engineer / Recipes (GMDRCPED)
should be established such that Standard, Minimum and Maximum Quantities are the same and reflect the desired planned order quantity.
This can then be seen in the Collection Workbench Process Effectivity
Advanced Supply Chain Planning/ Advanced Supply Chain Planning/ Collections/ View Collected Data (select the OPM organization), View By Items, Drill down Plans / Collections/ Category, click on the item, right click/ Bom/Routing/ Process Effectivity
as the Minimum and Maximum quantity
and in the Planner Workbench, Supply/Demand in the resultant planned order quantities
This only applies to ASCP Constrained Plans.
The Recipe Validity Rule
Process Engineer / Recipes (GMDRCPED)
should be established such that Standard, Minimum and Maximum Quantities are the same and reflect the desired planned order quantity.
This can then be seen in the Collection Workbench Process Effectivity
Advanced Supply Chain Planning/ Advanced Supply Chain Planning/ Collections/ View Collected Data (select the OPM organization), View By Items, Drill down Plans / Collections/ Category, click on the item, right click/ Bom/Routing/ Process Effectivity
as the Minimum and Maximum quantity
and in the Planner Workbench, Supply/Demand in the resultant planned order quantities
This only applies to ASCP Constrained Plans.